WASTE WATER TREATMENT PLANT OF FARSALA MUNICIPALITY

Contracting Authority: D.E.Y.A. (Public Utility of Water Suppl and Sewage) of Farsala
Contractor: KARKANIAS S.A.
Budget: 4.143.683,09 €

The Waste Water Treatment plant processes sewage and sludge of the Municipality of Farsala with secondary biological treatment in prolonged ventilation conditions with simultaneous stabilization of the sludge, as well as biological removal of nitrogen (nitrification-denitrification). This is followed by the disinfection (chlorination and dechlorination) of the treated sewage. For the treatment (thickening-dehydration) of excess sludge, a mechanical assembly of fattening bank and filter press has been installed.

According to the technical description including in the Bidding Documentation, the Plant’s capacity is as follows:

  • Population Equivalent: 16.000 residents
  • Waste water flow: 4.300 m3/d
  • Sewage flow: 50 m3/d
  • Organic flow BOD5: 900 kg/d
  • Suspended incoming solids: 960 kg/d
  • Total Nitrogen: 125 kg/d
  • Total Phosphorus: 40 kg/d
karkanias livade
karkanias livade
karkanias livade
karkanias livade

Design and Construction of Leachate Treatment Plant at Livade Landfill in Podgorica, Montenegro

Contracting Authority: Deponija D.O.O. Podgorica
Contractor: KARKANIAS S.A.
Budget: 1.683.055,00€

Livade Leachate Treatment Plant is constructed on the location of the existing sanitary landfill. Leachate will be transmitted from the existing leachate collecting pool no. 10. The design of the units performs for the estimated inlet flows of 80 m3/d, and 3.33 m3/h, with the possibility of expanding capacity up to 120 m3/day. Treated leachate will be either recycled to the landfill cells or discharged to the public sewage system of the City of Podgorica. Generated sludge after its treatment will be discharged to one of the landfill cells.

waste water λιανοκλάδι

WASTE WATER TREATMENT PLANT OF LIANOKLADI-YPATI

Contracting Authority: D.E.Y.A. (Public Utility of Water Suppl and Sewage) of Lamia
Contractor: KARKANIAS S.A.
Budget: 2.351.925,20€

The treatment method applied in the Plant consists of the activated sludge system with extended aeration and simultaneous stabilization of the sludge, biological removal of nitrogen (nitrification-denitrification), as well as biological and chemical removal of phosphorus. In addition, the Plant also included a tertiary treatment unit for the filtration and disinfection of the treated waste water (chlorination-dichlorination), while the excess sludge (mechanical thickening – dewatering) is treated by a decanted.

According to the technical description including in the Bidding Documentation, the Plant’s capacity is as follows:

  • Population Equivalent: 10.000 residents
  • Waste Water flow: 2.160 m3/d
waste water λιανοκλάδι
waste water λιανοκλάδι
karkanias wwtp dion
karkanias wwtp dion

WASTE WATER TREATMENT PLANT FOR THE MUNICIPALITIES AND COMMUNITIES LOCATED IN SOUTH PIERIA

Contracting Authority: Municipality of Dion-Olympos
Contractor: JV SKIRODEMA KATERINIS S.A.-KARKANIAS S.A.-ILIOU M.EDE
Budget: Estimated 19.822.422€

The Waste Water Treatment Plant for the Municipalities and Communities located in South Pieria is constructed at the area “Xiroziliano-Diodia” to the west of the National Road Katerini – Larissa, an area of 68 acres which is sufficient for the needs of the year 2040. The sewage treatment units are constructed at a special field approximately 250 m from the main site of the plant.

The capacity of the project is the following:

  • Population Equivalent: 150.000 residents
  • Daily Wastewater flow: 21.000m3/d
  • Sewage flow: 576m3/d
  • Organic Loading BOD5: 4.134Kg/d
  • Suspended solids: 5.706 kg/d
karkanias wwtp kos
karkanias wwtp kos

Tertiary treatment of the effluent in the Municipality of Kos island

Lorem Ipsum is simply dummy text of the printing and typesetting industry. Lorem Ipsum has been the industry’s standard dummy text ever since the 1500s, when an unknown printer took a galley of type and scrambled it to make a type specimen book. It has survived not only five centuries, but also the leap into electronic typesetting, remaining essentially unchanged.

It was popularised in the 1960s with the release of Letraset sheets containing Lorem Ipsum passages, and more recently with desktop publishing software like Aldus PageMaker including versions of Lorem Ipsum.

karkanias wwtp lamia
karkanias wwtp lamia

SUPPLYING AND INSTALLING OF THE ELECTROMECHANICAL EQUIPMENT IN THE WASTE WATER TREATMENT PLANT OF LAMIA

Contracting Authority: D.E.Y.A. (Public Utility of Water Suppl and Sewage) of Lamia
Contractor: KARKANIAS S.A.
Budget: 774.180.00 €

The Waste Water Treatment Plant has been constructed at a lowland rural area within the administrative limits of the Municipality of Lamia, at a road distance of approximately 6 km from the city center and 2.5 km from its limits. The area administratively belongs to the Municipality of Lamia and specifically to the area of Roditsa and occupies about 54 acres.

The scope of the project included:

  • The supply and installation of the new provisional electrical and mechanical equipment.
  •  The Civil Engineering auxiliary works during the installation of this equipment.
  •  The efficient operation and integration tests of the new equipment.
  •  The operation of the equipment for a period of three (3) months, since the completion of the works.
  •  The maintenance of the equipment for a period of twelve (12) months.
karkanias wwtp filipiada
karkanias wwtp filipiada

WASTE WATER TREATMENT PLANT OF FILIPPIADA MUNICIPALITY

Contracting Authority: Municipality of Ziros
Contractor: KARKANIAS S.A.
Budget: 2.903.980,00€

The Plant’s capacity is as follows:

  • Population Equivalent: 10.000 residents
  • Maximum Water flow: 2.544 m3/d
  • Sewage flow: 60 m3/d

The Waste Water Treatment Plant consists of the following units:

  1. Sewage inlet – Lifting pumping station
  2. Sewage Pretreatment unit and equalization tank
  3. Sewage Pretreatment unit (screening, grit and grease removal)
  4. Biological treatment unit
  5. Splitting manhole to the sewage subsidence tanks & dosing tanks of chemical dephosphorization
  6. Final sewage subsidence tanks
  7. Pumping station of recirculation and extraction of excess waste sludge
  8. Filtration unit
  9. Unit for disinfection and post aeration
  10. Sludge treatment (mechanical thickening and sludge dewatering)
  11. Leachate Pumping Station
  12. Deodorization systems
  13. Outlet manhole
  14. Accommodation and service buildings
waste water treatment

SEWAGE TREATMENT PLANT OF SOUTH THASOS

Contracting Authority: Municipality of Thasos
Contractor: JV KARKANIAS S.A. – DIALYNAS S.A.
Budget: 530.000€

The area where the unit is located is at a distance of about 3,8km east – northeast of the settlement of Skala Maries of the Municipality of Thasos. The constuction area of the Sewage Treatment Plant is located at about 130m upstream of the road section between the settlement of Maries and Prinos.

The Sewage Treatment Plant consists mainly of prefabricated units. Additionally, the disinfection unit and the septic and equalization tank assembly as well as the earthworks and other works for the reception, installation, connection and full operation of the compact units and configuration of the surrounding area, are also included.

The capacity of the plant, is 150m3 of sewage per day. Assuming the 15m3 capacity of a typical tanker, this supply corresponds to the reception of 10 tankers per day.

waste water treatment

WASTE WATER TREATMENT PLANT OF MOLOS SETTLEMENT

Contracting Authority: Municipality of Molos – Agios Konstantinos
Contractor: KARKANIAS S.A.
Budget: 1.442.268,76 €

The treatment method applied in the Plant consists of the activated sludge system with extended aeration and simultaneous stabilization of the sludge, biological removal of nitrogen (nitrification-denitrification), as well as biological and chemical removal of phosphorus. In addition, the Plant also included a treatment unit for the filtration and disinfection of the treated waste water (chlorination-dichlorination), while the excess sludge (mechanical thickening – dewatering) is treated by a decanted.

The Plant’s capacity is as follows:

  • Population Equivalent: 4.200 residents
  • Waste Water flow: 1.210 m3/d
waste water treatment

WASTE WATER TREATMENT PLANT OF KALLIRACHI-THASOS

Contracting Authority: Municipality of Thasos
Contractor: KARKANIAS S.A.
Budget: 1.424.000€

The Waste Water Treatment Plant will be located in a municipal area of 2.727.21 m2, of the settlement of Kallirachi and in particular is located 600 meters southwest of the settlement and is 1850 m from the highway Limenaria – Limenaria and 2000 meters from the sea.

Taking into account the tourist character of the area and its tourist development in recent years, the construction of a waste water treatment plant with a capacity of 3,000 equivalent inhabitants was chosen, so that it can also receive the sewage of Skala Kallirachis in the future and be able to cope with increased treatment needs, especially during the summer operating periods.

The unit includes the following sections:

  1. Compact wastewater pretreatment unit
  2. Equalization tank
  3. Compact biological treatment plants (MBBR)
  4. Filtration unit with drum filter
  5. Disinfection unit
  6. Sludge treatment
  7. Final disposal of treated sewage with a gravity pipe in an adjacent stream